Investment Trust JSC

Project in numbers:

18,000 m²
Work site area
424 pcs.
Quantity of lighting fixtures installed
TGC has completed the construction of a modern class A logistics complex — TRILOGY PARK. The complex includes five single-storey buildings. The total area of warehouses is about 107 thousand square meters. The project is one of the most successful projects in the field of industrial construction.
01
Design works
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories
05
Automated control systems

The works were carried out at the following sites:

Finished products warehouse (Building K36)

Project achievements:

The specific feature of this project is the guarantee of the key parameters such as illumination and power consumption saving under the contract for the term of 5 years. In case of any of the key parameters non-compliance, our company undertakes to eliminate any revealed “key parameter deviations” at its own cost.

As a result, we achieved the regulated illumination in the inter-shelf zone and loading/unloading area (mezzanine), using innovative lanterns with trussed cooling ribs BY 698 Green Perform G3 and Steinel motion sensor-based automated lighting control system for the light control.

The overall power saving reached over 65%.

The work of our specialists was highly appraised by our customer.

 

The following equipment was used at this facility:

BY 698P
BY 698P
WT 120C
WT 120C
IS 345 MX Highbay
IS 345 MX Highbay