Tobacco workshop
Our specialists have developed and implemented a unique project using motion sensors, illumination, push-button and touch screen lighting control panels by zones in automatic and manual mode. Control signals were transmitted via the DALI protocol using Dynalite controllers. As a result of the modernization of the lighting system, the savings in electricity consumption reached 64%, which is quite a significant achievement for LED lighting technologies in 2013.
Since the project was implemented with fully operational production, the work was carried out in accordance with strict timing, the working time in each allocated zone was strictly limited, when the site was launched even 15 minutes late, the tobacco factory suffered losses for non-production. The conditions for compliance with the timing were prescribed by the Customer in the contract, the penalties for non-compliance with the timing were of course enormous for our company.
All work was completed on time, without a single violation. The customer appreciated the work of our team at a high level.